List (New) under Project Section
List (New) under Project Section
- User logged into the workstatus.
- Click on project button.
- Select any project you want.
- Click on List(new).

- There are following columns available in List(new).
- Select the required project.
- the following details are shown:
- Task ID, with total number of task present.
- Assignee
- Task Status
- Task List
- Progress (%)
- Start Date
- End Date
- Estimated Hours with Total Hrs
- Invested Hours with Total Hrs
- Task Type
- Billing
- Priority
- Completed At
- Delay Status

- We can change the status of task from the task list (YET TO START,COMPLETE,IN PROGRESS, etc...).

- We can choose the Assignee from the task list, by click over dropdown.
- We can also search the assignee from the search option.
- We can also select all member as a assignee.

- We can change the Task Type status (Enhancement,Bug, etc...), by clicking over dropdown.

- We can change the **Billing **status (Billable,Non Billable, etc...), by clicking over dropdown.

- We can change the **Priority **status (Low,Medium,High, etc...), by clicking over dropdown.

- The Task Ellipsis (three-dot) menu provides quick actions to manage and perform operations on an individual task directly from the task list.
- View Task
- Click on Ellipsis when we hover over the task
- Allows users to view complete task information such as description, status, assignees, dates, and progress.
- Save as Task Template
- Saves the selected task as a template.
- Copy Task
- Creates a duplicate of the selected task.
- Copy Task Link
- Copies the direct link of the task.
- Move to Other Task List
- Moves the task to another task list.
- Complete Task
- Marks the task as Completed.
- Add to Favourite
- Adds the task to the favourite list.

- Add Tags
- We can add tags by clicking on tag button
- we can search tags
- we can add tags from the tag list

- Add Sub Task
- We can sub task to the task

- Move Task
- We can move task to another task

- Click on the Ellipsis (⋮) button in the top-right corner.

View Status
- When users click on View Status, the Task Status overview page is displayed. This page provides a visual summary of tasks based on their current statuses.
Task Status Chart
- A Donut chart displays the overall distribution of tasks by status.
- The centre of the chart shows the Total Tasks count.
- Each coloured segment represents a different task status.

Group By
- The Group By option allows users to organise the task list by grouping tasks based on specific criteria.
- Status – Groups tasks based on their current status.
- Assignee – Groups tasks by the assigned user.
- Priority – Groups tasks according to priority level.
- Due Date – Groups tasks based on their due dates.
- Milestone – Groups tasks under their respective milestones.
- Tag – Groups tasks by assigned tags.
- Task Type – Groups tasks based on task type.

- Also Group by List
=> Enable the Also group by list toggle to further group tasks by task list within the selected grouping.
=> When we enable Also group by list then Milestone option disable.

Columns
- Allows users to show, hide, and rearrange columns in the task list, click on save.

Export
- Enables users to export the task list data.
- In PDF or CSV format

Bulk task operations are available in the List (New) view.
For detailed information on how to use bulk operations, please refer to the link below.
https://support.workstatus.io/en/article/bulk-operations-on-task-13fr1ht/?bust=1769759067918
Updated on: 30/01/2026
Thank you!